School Calendar

Calendar

School Board News

Upcoming Board Meetings

August 3, 6:30 p.m. Work Session            Location: Old Village Hall, Remer
August 17, 6:30 p.m. Regular School Board Meeting          Location:  Old Village Hall, Remer

Candidate Filing for Special Election

The period for filing affidavits for candidacy for the office of school board member to fill a vacancy in the term expiring January 7, 2019 of Independent School District #118 shall begin on Tuesday, August 1, 2017, and shall close at five o’clock p.m. on Tuesday, August 15, 2017. Affadavits of Candidacy are available from the District Office, which is located in the 1st National Bank of Walker building at the corner of Hwy 200 and 1st Ave. in Remer.
The special election shall be held on Tuesday, November 7, 2017.


The District Office Has Moved!

Due to the construction project the District Office has moved into temporary offices in 1st National Bank in Remer at the corner of Main St and 1st Avenue. There is a door on Main Street for access to the District Office only, from 8:00 - 4:00 pm Monday through Friday. A big thanks to 1st National Bank for allowing the District to use these office spaces this summer!
 


Student Information Systems

Click on the picture to go to the parent/student portal. You can view your child's lunch account, deposit money in to the account, update your contact info, and check on your child's attendance or grades.

If you want to go to Schoology.com click on this link: http://www.schoology.com


If you need help accessing the Parent Portal, please contact one of the school offices.
 
 

Building For The Future

July 27, 2017 - 23 days left
The new building is almost finished. Workers are laying tile on the floors, installing the gym floor, polishing the commons area concrete floor, installing kitchen equipment, and finishing baseboard.  Cleaners are coming to begin the final cleaning.
In the old high school, which will become the new elementary, workers are busy running cable and wires, putting up sheetrock, installing doors and windows, finishing ceilings and many other things. Each day there are over 120 workers on site.
Site work outside has also begun. Curbs and cutters will start to be poured next week. All the old cement block has been crushed and will be spread on roadways and parking lots before they are tarred.
It won't be long before we'll be able to show off the building to the students, families and communities.

June 30, 2017

Work on the buildings continues......
This is the east side of the new building.This picture shows the front entrance.Her is the west side of the building after the demolition of the old buildings.This big pile of concrete will be crushed and used on the gravel driveways.This picture was taken at the west entrance to the parking lot, looking back at the buildings.New Dugout is being built
The custodians are working on the grounds and fields this summer, including building new dugouts.

June 15, 2017 - 64 days left of construction
Highlights of the last month: the doors have been installed on the main entry. Painting is complete in the new building. All of the kitchen appliances have been delivered, and will be installed by June 21. Bathrooms have tile and fixtures; the partitions will be installed beginning June 15. Ceilings are almost complete in the new building. Demolition of the elementary building and WPA will begin on June 19. The construction project is on schedule.



May 3, 2017 - 3.5 months left of construction
The interior spaces in the new building are being finished: the concrete floors in the commons area and hallways are being burnished; walls are being painted, cabinets are going in, the kitchen walls and floor has been tiled and appliances are being installed; ceiling grids are being completed; bathrooms are being tiled. It's a busy place, with over 60 workers on site each day. In addition, planning and preparation is happening for the high school remodel. Staff members having begun packing in preparation for Move Out Day on May 18.
The Oversight Committee continues to meet semi-monthly.  The next meeting is June 14, 2017 - 8:30 a.m. at District Office summer offices at 1st National Bank in Remer.

Members of the Oversight Committee are:
Pat Rendle, Interim Superintendent
Jared Johnson, Head Custodian
Clayton Lindner, Principal
Ellie Hill, Business Manager
Dan Switzer, School Board Chair
Linda Knox, School Board Member
Marc Ruyak, School Board Member
Etta Shepard, alternate, School Board
Aaron Kriens, FJJ,  Project Manager
Arif Quraishi, FJJ,  Program Manager

If you have any questions, please feel free to contact Principal Lindner at (218) 566-2351 ext 2010

 
Cabinets in one of the new classroomsWorkers are polsihing the conrete floor inthe Commons area.